D23
June 2026Q. 1(d)2 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(d)What remedies are available to a buyer under Section 12 of the Act, if the advertisement, prospectus or model flat contains false or incorrect representations ?

December 2024Q. 2(c)(i)2 marksSyllabus 2022
Show the facts common to all parts of Q. 2

(c)“Neev Builders” launched a luxury housing project, issued a prospectus and advertised that these spacious apartments would have scenic views and all the global amenities. Umesh was impressed by this advertisement and made advance payment to book an apartment.

However, later discovered several significant disparities and amenities from the promises made in the advertisement. Umesh wants to withdraw from the project.

Answer the following questions as per the provisions of Real Estate (Regulation and Development) Act, 2016 :

(i)Explain the obligations of Neev Builders regarding veracity of the advertisement or prospectus.

December 2024Q. 2(c)(ii)3 marksSyllabus 2022
Show the facts common to all parts of Q. 2

(c)“Neev Builders” launched a luxury housing project, issued a prospectus and advertised that these spacious apartments would have scenic views and all the global amenities. Umesh was impressed by this advertisement and made advance payment to book an apartment.

However, later discovered several significant disparities and amenities from the promises made in the advertisement. Umesh wants to withdraw from the project.

Answer the following questions as per the provisions of Real Estate (Regulation and Development) Act, 2016 :

(ii)Can Umesh withdraw from the project ?

June 2026Q. 1(b)2 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(b)Is booking amount up to 20% of the apartment cost valid ? Give reason.

June 2026Q. 1(g)3 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(g)What are the promoter’s obligations regarding execution of conveyance deed and transfer of common areas under Section 17 of the Act ?

June 2026Q. 1(e)2 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(e)If Devendra decides to withdraw due to delay in possession, what relief is available to him under Section 18(1) of the Act ?

June 2026Q. 1(f)2 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(f)If Surendra does not withdraw from the project and continues as an allottee, state the promoter’s liability for delayed possession under Section 18(1) of the Act ?

June 2024Q. 3(a)5 marksSyllabus 2022

(a)Rajeev booked a Flat in a housing scheme named ‘Alpha Tower’ Launched by Alpha Pvt. Ltd.

by paying the booking amount and executing the ‘Buyer’s Agreement’. As per the Buyer’s Agreement’, Flat was to be delivered with 3 years of the Agreement but the promoters of the Company failed to deliver the Flat even after 5 years. Rajeev wants to withdraw from the project and wants the refund of amount paid. Discuss as per the provisions of Real Estate Regulation and Development Law whether Rajeev can withdraw from the Project ?

What is the remedy available to Rajeev, if he does not wish to withdraw from the project ?

December 2025Q. 2(b)(i)3 marksSyllabus 2022

(b)State the penalty to be imposed in the following cases as per the provisions of the Real Estate (Regulation and Development) Act, 2016 :

(i)A Housing Scheme Project was launched by XYZ Ltd. The Promoters of the company started the selling of plots and booking of apartments without registering this project with the Real Estate Regulatory Authority.

June 2025Q. 3(c)5 marksSyllabus 2022

(c)A housing scheme project was launched by ABC Ltd. in 2015, which is still ongoing and has not received a completion certificate. On 1.5.2016, the Real Estate (Regulation and Development) Act, 2016 (RERA Act) came into force. ABC Ltd. now wants to register this project with the Real Estate Regulatory Authority under the RERA Act. Advise ABC Ltd.

whether it can register this project. Also, state which projects are exempt from the ambit of the RERA Act.

June 2026Q. 1(c)2 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(c)If the promoter provided false information regarding land title at the time of registration, what penalty may be imposed under Section 60 read with Section 4 ?

December 2025Q. 2(b)(ii)2 marksSyllabus 2022

(b)State the penalty to be imposed in the following cases as per the provisions of the Real Estate (Regulation and Development) Act, 2016 :

(ii)A Housing Scheme Project was launched by ABC Ltd. The promoter of the company filed an application for the registration of this project giving an affidavit stating that seventy per-cent of the amounts realised for the real estate project from the allottees, from time to time, shall be deposited in a separate account to be maintained in a scheduled bank to cover the cost of construction and the land cost and shall be used only for that purpose. But, in reality, that account was never opened.

June 2026Q. 1(a)2 marksSyllabus 2022
Show the facts common to all parts of Q. 1

Sunshine Builders Pvt. Ltd. launched a residential project named Green Valley Residency in 2023 comprising 120 apartments on 2,000 sq. meters of land. The promoter started advertising the project through brochures and online portals, promising possession within 24 months and highlighting amentities such as a clubhouse and landscaped gardens.

The promoter accepted booking amounts up to 20% of the apartment cost from several buyers without executing a registered agreement for sale. Some buyers paid advances based solely on the advertisement and model flat displayed at the site office.

Sunshine Builders applied for registration of the project before the Real Estate Regulatory Authority (RERA) but failed to disclose certain pending litigation relating to the title of the land.

The Authority did not communicate approval or rejection within 30 days. Meanwhile, the promoter continued construction and marketing activities.

After two years, the project remained incomplete and possession was delayed by 12 months beyond the promised date. Further, certain promised amenities were not constructed. Devendra, an allottee, decides to withdraw and seek refund, while another allottee, Surendra, wants possession along with compensation for delay. The promoter has also neither executed conveyance deeds nor handed over the common areas despite obtaining the occupancy certificate. Aggrieved allottees have now approached RERA seeking relief.

Based on above facts, answer the following under the Real Estate (Regulation and Development)

Act, 2016 :

(a)What is the legal effect if RERA neither grants nor rejects registration within 30 days ?

No questions in this chapter match these filters.